Week | Dates |
Activities |
Details |
1 |
Jan 27-31 |
Sprint 1 Planning
Sprint 1
|
- organize the team
- review existing project resources
- learn development technology
- determine which user stories and use cases are completed
- meet the clients
- write any new user stories
- prioritize remaining user stories
- estimate and complete tasks for highest priority user stories
- standups at least twice a week starting Week 2
- maintain the Board
- DELIVER: user stories, use cases, CRC cards if appropriate, accurate Board, code
|
2 |
Feb 3-7 |
Sprint 1
Sprint 1
|
3 |
Feb 10-14 |
Sprint 1
Sprint 1 Review + Sprint 2 Planning |
4 |
Feb 17-21 |
Sprint 2
Sprint 2
|
- develop tasks for highest priority stories
- estimate tasks
- complete tasks for highest priority stories
- standups at least twice a week
- maintain the Board
- DELIVER: any additional of above, accurate and detailed Board, code
|
5 |
Feb 24-28 |
Sprint 2
Sprint 2 Review + Sprint 3 Planning
|
6 |
Mar 3-7 |
Sprint 3
Sprint 3
|
- develop tasks as indicated by sprint backlog and priorities
- standups at least twice a week
- maintain the Board
- DELIVER: any additional of above, accurate and detailed Board, code
|
7 |
Mar 10-14 |
Sprint 3
Sprint 3 Review
|
7 |
Mar 13 |
Final Project Presentation. 11:30 a.m. Thursday March
13 |